EETN completes first pile driving contract with less than 1% of piles needing remediation

EETN was awarded a contract to install 7MW DC by LendLease.  The installation was in Halifax NC and was scheduled for 3 months of site work.  EETN installed Solar FlexRack's G3X contour following racking system.  The installation included 2400 driven piles for racking mount.  EETN's pile driving team completed the project with 5 piles needing remediation. 

"I am extremely impressed with what the team was able to accomplish.  We took on a task that was relatively new to us and our team was nearly perfect on the first attempt. I can't say enough about the quality of people we have at EETN"   - Robbie Thomas, President

The EETN team reached mechanical completion of this project on March 31, 2017.